Pacific Region Operational Statement
Clear-Span Bridges
Version 3.0 (PDF)
This Operational Statement applies to the construction of small-scale
bridge structures that completely span a watercourse without altering the
stream bed or bank, and that are a maximum of two lanes wide. The bridge
structure (including bridge approaches, abutments, footings, and
armouring) is built entirely above the
high water mark (HWM). A clear-span bridge is preferred to a culvert
as no structures are placed on the stream bed and therefore there is no
alteration of natural channel processes.
Clear-span bridge construction has the potential to negatively affect
riparian habitat. Riparian vegetation occurs adjacent to the watercourse
and directly contributes to fish habitat by providing shade, cover and
areas for spawning and food production. Only the vegetation required to
accommodate operational and safety concerns for the crossing structure and
approaches, within the right-of-way, should be removed. Stormwater run-off
and the use of machinery can introduce deleterious substances to the water
body and result in erosion and sedimentation.
Fisheries and Oceans Canada (DFO) is responsible for protecting fish
and fish habitat across Canada. Under the Fisheries Act no one may
carry out a work or undertaking that will cause the harmful alteration,
disruption or destruction (HADD) of fish habitat unless it has been
authorized by DFO. By following the conditions and measures set out below
you will be in compliance with subsection 35(1) of the Fisheries Act.
The purpose of this Operational Statement is to describe the conditions
under which it is applicable to your project and the measures to
incorporate into your project in order to avoid negative impacts to fish
habitat and maintain passage of fish. You may proceed with your clear-span
bridge project without a DFO review when you meet the following
conditions:
- the bridge is placed entirely above the
high water mark (HWM),
- there is no alteration of the stream bed or banks or infilling of
the channel,
- the bridge is no greater than two vehicle lanes in width, does not
include sidewalks and biking lanes and does not encroach on the natural
channel width by the placement of abutments, footings or rock armouring
below the HWM,
- the work does not involve the clearing of riparian vegetation –
removal of select plants with the road right-of-way can occur to meet
operational and/or safety needs,
- your project does not require multiple bridge crossings over the
same watercourse, and
- you incorporate the Measures to Protect Fish and Fish Habitat
when Constructing Clear-Span Bridges listed below in this
Operational Statement.
If you cannot meet all of the conditions listed above and cannot
incorporate all of the measures listed below then your project may result
in a violation of subsection 35(1) of the Fisheries Act and you
could be subject to enforcement action. In this case, you should contact
the DFO office in your area if you wish to obtain DFO’s opinion on the
possible options you should consider to avoid contravention of the
Fisheries Act.
You are required to comply with all municipal, provincial,
territorial and/or federal legislation that applies to the work being
carried out in relation to this Operational Statement. In British
Columbia, please contact the
Water Stewardship Division, Ministry of Environment for information on the Provincial Water Regulation
notification requirements when planning to construct clear-span bridges in or around BC waters.
The activities undertaken in this Operational Statement must also
comply with the Species at
Risk Act. For
general information on SARA species contact DFO
by email.
If you have questions regarding this Operational
Statement, please refer to the list of
Frequently Asked Questions or contact DFO Regional Headquarters
at 1-866-845-6776.
Please notify DFO 10 working days before starting your work by filling
out and sending the Pacific Region
Operational Statement notification form directly to DFO Regional
Headquarters. This information is requested in order to evaluate the
effectiveness of the work carried out in relation to this Operational
Statement. It is recommended that you keep a copy of the Operational
Statement at the work site to demonstrate to Habitat and Fishery Officer
staff that the conditions and measures, as outlined in the OS, are being
followed.
Area of Application
This Operational Statement applies to the province of British Columbia
and Yukon Territory freshwater systems only.
Measures to Protect Fish and Fish Habitat when Constructing
Clear-Span Bridges
1. Minimize the
riparian area temporarily disturbed by access activities along the
adjacent upland property. Use existing trails, roads, or cut lines
wherever possible to avoid disturbance to the riparian vegetation.
2. Avoid building on
meander bends, braided streams, alluvial fans, active flood plains, or any
other area that is inherently unstable and may result in the alteration of
natural steam functions or erosion and scouring of the bridge structure,
3. While this
Operational Statement does not apply to the clearing of riparian
vegetation, the removal of select plants within the road right-of-way
(ROW) may be required to meet operational and/or safety concerns for the
crossing structure and the approaches. This removal should be kept to a
minimum and within the road right-of-way. When practicable, prune or top
the vegetation instead of uprooting.
4. Ensure that the
clear span bridge is properly designed to address river and channel
processes at flows above the ordinary high water mark.
5. Design and construct
approaches so that they are perpendicular to the watercourse to minimize
loss or disturbance to riparian vegetation.
6. Design the bridge so
that stormwater runoff from the bridge deck, side slopes and approaches is
directed into a retention pond or vegetated area to remove suspended
solids, dissipate velocity and prevent sediment and other deleterious
substances from entering the watercourse.
7. Generally there are
no restrictions on timing for the construction of clear-span structures as
they do not involve in-water work. However, if there are any activities
with the potential to disrupt sensitive fish life stages (e.g., crossing
of watercourse by machinery), these should adhere to appropriate fisheries timing
windows.
Machinery fording the watercourse to bring
equipment required for construction to the opposite side is limited to a
one-time event (over and back) and should occur only if an existing
crossing at another location is not available or practical to use. A
Temporary Ford Stream Crossings Operational Statement is also
available.
7.1. To exercise this option,
the stream bed at the fording site must be comprised of stable gravel or
bedrock and the stream banks must be low and stable.
7.2. If minor rutting is
likely to occur, stream bank and bed protection methods (e.g., swamp mats,
pads) should be used provided they do not constrict flows or block fish
passage.
7.3. Grading of the stream
banks for the approaches is not permitted.
7.4. If the stream bed and
banks are steep and highly erodible (e.g., dominated by organic materials
and silts) and erosion and degradation are likely to occur as a result of
equipment fording, then a temporary crossing structure or other practice
should be used to protect these areas.
7.5. Time the one-time
fording to prevent disruption to sensitive fish life stages by adhering to
appropriate fisheries timing
windows.
7.6. Fording should occur
under low flow conditions and not when flows are elevated due to local
rain events or seasonal flooding.
8. Install effective sediment
and erosion control measures before starting work to prevent the entry of
sediment into the watercourse. Inspect them regularly during the course of
construction and make all necessary repairs if any damage occurs.
9. Operate machinery on land
(above the HWM) and in a manner that
minimizes disturbance to the banks of the watercourse.
9.1. Machinery is to arrive
on site in a clean condition and is to be maintained free of fluid leaks,
invasive species and noxious weeds.
9.2. Wash, refuel and service
machinery and store fuel and other materials for the machinery away from
the water to prevent any deleterious substance from entering the water.
9.3. Keep an emergency spill
kit on site in case of fluid leaks or spills from machinery.
9.4. Restore banks to
original condition if any disturbance occurs.
10. Use measures to prevent
deleterious substances such as new concrete (i.e., it is pre-cast, cured
and dried before use near the watercourse), grout, paint, ditch sediment
and preservatives from entering the watercourse.
11. No debris to remain
within the high-water mark or placed into a stream.
12. Stabilize any waste
materials removed from the work site to prevent them from entering the
watercourse. This could include covering spoil piles with biodegradable
mats or tarps or planting them with preferably native grass or shrubs.
13. Vegetate any disturbed
areas by planting and seeding with native trees, shrubs or grasses and
cover such areas with mulch to prevent erosion and to help seeds
germinate. All seeding and/or planting trees should follow the DFO
guidance on
Riparian Revegetation. If
there is insufficient time remaining in the growing season, the site
should be stabilized (e.g., cover exposed areas with erosion control
blankets to keep the soil in place and prevent erosion) and vegetated the
following spring.
13.1. Maintain effective
sediment and erosion control measures until re-vegetation of disturbed
areas is achieved. |